Region Neyruz-sur-Moudon - Will there ever be a cell tower?

Hello, Small share 😥... 12 years of waiting and promises every year from Swisscom to cover this part of the canton with mobile antennas. 2026... still nothing in sight. A Swisscom map that "boasts" of providing 5G outdoors... but even with a MikroTik ATL 5G R16 4x4 MIMO CPE modem with 16 dBi gain pointed towards the nearest antenna... the only "5G" captured is 4G+ aggregation... whereas an average user does not have such a configuration. 5G? 🤔 Hem, hem... the blue giant is not very honest
Translated from French
2
6
6 comments
LeutrimShallti@LeutrimShallti7 Aug 2026edited
Hello, Indeed, I have looked into it: there is indeed a building permit application filed on 13.03.2020 for Swisscom and Sunrise. However, in my opinion, the legal deadline has now passed and a new application will probably have to be filed. This application concerned the following address: Chemin du 1er Août 1515 Neyruz-sur-Moudon. Furthermore, Swisscom filed a new building permit application on 03.05.2024 at the following address: Les Rutannes 1, 1515 Neyruz-sur-Moudon. Generally, construction work begins approximately two years after the permit application. I will look into it and keep you informed.
Translated from French
0
M@Maitre2Citrouille23 Aug 2026@LeutrimShallti
I found this investigation with your information. But I cannot figure out if the license was issued or not.
Translated from French
0
LeutrimShallti@LeutrimShallti23 Aug 2026@Maitre2Citrouille
Hello, Yes, I have received several pieces of information, but I am still waiting for a response from the municipality. The building permit at the address Les Rutannes 1, 1515 Neyruz-sur-Moudon was issued by the municipality on August 8, 2024. The legal deadline for construction is 2 years from the date the permit was issued. Since the deadline has passed, art. 118 LATC states that a building permit is in principle expired if the work has not started within a period of two years. In justifying circumstances, the municipality may extend the validity by one year. I am therefore waiting for confirmation as to whether we are in this case or if the operators will have to submit a new building permit application. Regarding the building permit application at Chemin du 1er Août 1515 Neyruz-sur-Moudon, the municipality has not yet issued the building permit. I will get back to you as soon as I receive the response from the competent authorities. Warm regards,
Translated from French
1
Hello Leutrim, woaw I wasn't expecting to receive so much information. Thank you.
Translated from French
1
LeutrimShallti@LeutrimShallti4 d ago@Maitre2Citrouille
Hi, I received confirmation from Swisscom that the antenna at rue Les Rutannes 1 is under construction. Commissioning is scheduled for November 11, at the latest end of November 2026. Feel free to confirm that the construction site has indeed started 💪
Translated from French
0
LeutrimShallti@LeutrimShallti4 d ago@Maitre2Citrouille
Hi, I received confirmation from Swisscom that the antenna at rue Les Rutannes 1 is under construction. Commissioning is scheduled for November 11, at the latest end of November 2026. Feel free to confirm that the construction site has indeed started 💪
Translated from French
0